Overview
Cost element grouping is an SAP feature that offers flexibility
in categorizing cost elements into groups. You can select an alternative
cost element structure for some of your reports by selecting different
cost element groups.
The reports which have a Cost Element Group field are the
Summary Statement, Detail Transaction Report, and the 24 Column
Account Managers Report. For example, if you run the Summary Statement
with the default cost element group, CEMIT-0, the report will display
complete information for all cost elements in a standardized order.
Some cost element groups may display more restricted views of activity;
for example, CEMIT-EX would display only expenses and would exclude
all revenue activity.
Cost element groups preceded with "CEMIT" are designed for use
with reports, and to ensure the completeness of your report it is
recommended that you use them. In addition to CEMIT-0, there are
other cost element groups: CEMIT-1, a slightly more summarized version
that includes settlement; CEMIT-3, a version that matches the groupings
of the Fund Analysis; and CEMIT-4, a grouping that matches the Brown
Book. See Cost
Element Group Descriptions for others.
top
Displaying
Information on a Cost Element Group
1. Click on the Matchcode button
(PC: )
in the Cost Element Group field on a report. (Click in the
field if the Matchcode button is not displayed.)
Result: A list of all cost element groups for the report
is displayed.

2. Click the eyeglass icon
to the right of the cost element group; CEMIT-0 for example.
Result: The "Display Cost element group: Structure"
screen is displayed.

3. Click the folders to drill down individual cost elements or
to roll up to cost element subgroups.
|
|
Note
|
If there are no folders,
then you cannot drill down further on the cost element
subgroup.
|
|
|
Other Display Options
|
| All Cost Element Subgroups |
Click on the highest level cost element group (CEMIT-0 for
example) and the green Expand All button . |
| Only the Highest Level Cost Element Subgroups |
Click on the highest level cost element group (CEMIT-0 for
example) and the red Collapse All button . |
| Individual Cost Element Information (if
you have authorization) |
Double-click on the individual cost element. |
4. Click on the Back button
until you return to the listing of cost element groups.
5. Click on a cost element group to select it for the report.
top
Setting the
Display Text Option (for initial setting)
If you can't display the cost element names, you may need to set
the Display Text Option on the "Display Cost element group:
Structure" screen.
1. Follow the menu path: Extras>>Default settings>>Structure.
Result: The "Default Settings" window is displayed.

2. Under Master Data, click in the box next to
Breakdown intervals and Display
texts.
3. Under Structure, click in the box next to
Display texts.
4. Click the Enter button .
Result: You return to the "Display Cost element group: Structure"
window.
5. Click the cost element group.
6. Click the Expand All button .
Result: The names of the cost element subgroups are displayed
to the right. These settings will remain in effect unless changed.
top
|